Track Records

YearClientWork Description
2016 FINANCIAL PARK (LABUAN) SDN BHD To conduct fabrication on seawage 'A' frame
2016 FINANCIAL PARK (LABUAN) SDN BHD To conduct portable lifting 'A' frame - Kerupang
2016 FINANCIAL PARK (LABUAN) SDN BHD Motor servicing for 20kW pump motor
2016 DORSETT GRAND LABUAN (HOTEL) Overhaul & rewind Teco Electric Chiller water pump motor 22kW
2016 DORSETT GRAND LABUAN (HOTEL) To install & conduct testing at Dorsett Hotel magnetic 3/4Hp Century Pool/Jetted Tub motor & pump
2016 DORSETT GRAND LABUAN (HOTEL)D Overhaul & rewind terminal box 5.5kW motor
2016 DORSETT GRAND LABUAN (HOTEL) Overhaul & rewind Exhaust Fan motor 3.7kW (5Hp)
2016 INTERNATIONAL SHIPCARE SDN BHD Troubleshoot & rectify 400KVA Generator Alternator (G2)
2016 INTERNATIONAL SHIPCARE SDN BHD Overhaul & rewind 90kW
2016 INTERNATIONAL SHIPCARE SDN BHD To perform rewind stator winding 400KVA Generator (G1)
2016 INTERNATIONAL SHIPCARE SDN BHD Troubleshoot & rectify 400KVA Generator Alternator (G1)
2016 EMPADA SDN BHD Overhaul & servicing 29kW motor
2016 EMPADA SDN BHD Overhaul & rewind 78kW motor
2016 EMPADA SDN BHD Overhaul & servicing 30kW motor
2016 EMPADA SDN BHD To convert 2.2kW from 50Hz to 60Hz test run motor c/w report
2016 BUMI ARMADA SHIP MANAGEMENT SDN BHD To conduct troubleshoot FIFI port & Stand board compressor clutch solenoid valve not function AT24
2016 BUMI ARMADA SHIP MANAGEMENT SDN BHD Troubleshoot, repair & replace broken part for remote valve P1,P2,P3 & conduct functioning test AT25
2016 BUMI ARMADA NAVIGATION SDN BHD Troubleshooting Armada Firman 2, repair & maintenance to replace 2 unit contactor & conduct functioning test
2016 BUMI ARMADA SHIP MANAGEMENT SDN BHD Repair main circuit Breaker and conduct functioning test AT26
2016 BUMI ARMADA SHIP MANAGEMENT SDN BHD Troubleshoot generator set and rectify (exciter diode burn) AT6
2016 BUMI WANGSA TMS SDN BHD To perform test run for submersible motor pump c/w report
2016 ARTHA VISION SOLUTION To do inspection and recertification of EXD Junction Box
2016 JDC To perform overhaul 80kW Ballas Water Pump motor Naga 1 (No. 317)
2016 JDC To perform overhaul 63 kW AC motor Naga 1 (188)
2016 SERBA DINAMIK SDN BHD To perform test run for Submersible pump c/w report 10HP SME
2016 SERBA DINAMIK SDN BHD Perform extra 3 lead connection for 250HP SME new motor 186kW , Electric Fire Water Pump motor P660/F23
2016 SERBA DINAMIK SDN BHD Overhaul for submersible motor P670 30kW motor
2016 SCOMI OILTOOLS SDN BHD Balancing for scroll and bowl DE1000.
2016 TECHNOFIT MARINE & OFFSHORE SERVICES SDN BHDD Provision of Overhaul & Rewind Dual-Motor for Hartmann Offshore (UOS Navygitor) 37/54kW motor
2016 HALLIBURTON ENERGY SERVICES SDN BHD To refurbish 1 unit rotating assembly DE7200 & DE1000 Centrifuge pump PCSB Limbayoung 4 DSM 1 Project
2016 JDC Overhaul and Rewind 600kW DC motor
2015 MDPC Rewind and repair motor 78kw.
2015 EMPADA SDN BHD Overhaul and rewind GS-Pump 160kw.
2015 EMPADA SDN BHD Overhaul and rewind motor 291kw.
2015 EMPADA SDN BHD Servicing FD Fan motor 380kw.
2015 EMPADA SDN BHD Overhaul VRU LS Electric motor KM-T7000 (900kw)
2015 JDC Overhaul and rewind air compressor motor 184kw.
2015 JDC Overhaul AC motor 63kw.
2015 SCOMI OILTOOLS SDN BHD Balancing for scroll and bowl DE1000.
2015 EMPADA SDN BHD Overhaul and rewind dual speed motor 380/170kw.
2015 OCEANCARE CORPORATION SDN BHD Servicing Generator No.1 (Y4) LCOT.
2015 MASER & QUARTZELEC SERVICES SDN BHD Overhaul VRU LS Electric motor KM-T7000 (900kw)
2015 PETRONAS CHEMICALS METHANOL SDN BHD HV motor servicing GM-651 C & GM-651 D
2015 PETRONAS CHEMICALS METHANOL SDN BHD LV/MV and HV motor servicing, preventive maintenance and site installation at Methanol Plant 2 during Petronas TurnAround (TA).
2015 PETRONAS CHEMICALS METHANOL SDN BHD Overhaul and servicing CM-102 motor
2015 OCEAN VANTAGE ENGINERING SDN BHD Overhaul 125kw motor MK6 anchor jewelry
2015 EMPADA SDN BHD Overhaul and rewind dual speed sea water pump motor 45/110kw
2015 HALLIBURTON ENERGY SERVICES SDN BHD To perform blasting and balancing for scroll and bowl DE7200/DE1000
2014 PETRONAS CHEMICALS METHANOL SDN BHD/td> HV and LV motor servicing during Petronas TurnAround.
2014 SERBA DINAMIK SDN BHD To inspect / service 225kw submersible motor.
2014 SERBA DINAMIK SDN BHD To inspect / service 250hp submersible motor.
2014 SCOMI OILTOOLS SDN BHD Couple and test run submersible motor / pump complete with report.
2014 PETRONAS CHEMICALS METHANOL SDN BHD Provision of pre-commissioning and commissioning work for electrical and instrument scope for Jetty refurbishment project at Plant 1.
2013 SCOMI OILTOOLS SDN BHD Upgrade DOL starter panel from 75hp to 100hp.
2013 SCOMI OILTOOLS SDN BHD Overhaul 75hp submersible motor / pump A.
2013 PETRONAS CHEMICALS METHANOL SDN BHD Installation of Methanol metering system and supply of material / manpower at PCMSB Plant 1 (Jetty).
2013 PETRONAS CHEMICALS METHANOL SDN BHD CM-102 SR 10176510, HV motor servicing and site installation at Petronas Methanol Plant 1. GM-151B SR 10176537, HV motor servicing & site installation at Petronas Methanol Plant 1.
2013 PETRONAS CHEMICALS METHANOL SDN BHD To supply of 110Vac distribution panel for DCS upgrading at Petronas Methanol Plant 1.
2013 PETRONAS CHEMICALS METHANOL SDN BHD LV motor servicing & site installation at Petronas Methanol Plant 1. (CM-601A)
2013 PETRONAS CHEMICALS METHANOL SDN BHD Installation of electrical / instrument equipment and supply of material for PCMSB Plant 1 (Jetty).
2013 PETRONAS CHEMICALS METHANOL SDN BHD Provision of field instrument calibration, servicing & testing during August shutdown at PC Methanol Plant 2.
2013 PETRONAS CHEMICALS METHANOL SDN BHD Provision of engineering, procurement, installation & commissioning for 110Vac modification work at Petronas Methanol Plant 1.
2013 PETRONAS CHEMICALS METHANOL SDN BHD HV motor servicing & site installation during turnaround at Petronas Chemicals Methanol Plant 1.
2013 TANJUNG MAINTENANCE SERVICES SDN BHD Flair aviation lighting, distribution board replacement & cable laying at Petronas Chemicals.
2013 TANJUNG MAINTENANCE SERVICES SDN BHD Overhaul and rewind 380kw motor, renew shaft and machine new bearing caps etc.
2013 JAPAN DRILING COMPANY Manpower for electrical work and Ex inspection
2013 TANJUNG MAINTENANCE Overhaul and rewinding AC motor 76 units.
2013 SERBA DINAMIK

To supply HOTRN F 4c x 16mm submersible cable to perform external splicing kit c/w IR test after submerge inside water for 24 hours.

Conduct free load test to record the final parameter.

2013 EMAS OFFSHORE To calibrate fuel oil flow meter, to run 3 times comparison and accuracy test each unit flow meter against our master flow meter. All test comes with calibration certificate and report accordingly with accuracy +- 0.5% acceptance tolerance. To repair and service 3 unit malfunction flow meter totalizer before comparison test.
2013 PETRONAS METHANOL (L) SDN BHD To overhaul and rewind 500kw Hv motor
2013 PETRONAS METHANOL (L) SDN BHD

Line : 10 SE101060201 high Voltage Non-Explosion Proof

Mo GM - 651 spare motor servicing/rewinding.

2013 KESUMA SHIPPING To supply materials offshore manpower fabrication to carry out cable fray laying on board RIG NAGA 1 (JAPAN DRILING COMPANY)
2013    Emas Offshore Sdn Bhd     Ship repant and maintenance
2012

Mega -Methanol (PMLSB)

JDC-Japan Drilling Company

Complete servicing and modifications to 14 capasitor banks

E&I erection and manpower supply NAGA 1 RIG

2011 Sabah Forest Industry(SFI) Rejuvenation E&I erection for all Transformers, LT and HT panels totaling 400 ++ units , AC drives, motors ranging from 1.1 thru 1.5MW , 11, 30 MW Steam Generator, PLC DCS systems , Fibre-optic cable laying and termination , busduct installation and commisioning , earthing and Lightning plantwide totaling some 300 ++ earthpits and protection systems, , AL cabling up to 3.5 c x 350 mm sq , totaling some 87,800 mtrs ( mostly on pipe rack at + 11.5 Mtr above ground ) , termination and commissioning of 415 V , 690 V &11KV equipment and ancillaries
2010 ABF 12 TA Remove & Install ,in situ servicing of 72 nos motors ranging from 15 KW to 1.2 MW
2009 PMLSB Plant Rejuvenation & Turnaround project
2005-2007 IEC Ex Implemented IEC Ex certification to 1st workshop in Malaysia
2004 Barton field - SSPC In-situ refurbishment of 330 KW Kato Alternators
2002 Gas Malaysia Modification to 6” cl.300# ball valves
2002

KTMB

Motor rewinding 50kw

2002 Mudajaya Holdings Design and complete installation of Fil-tomat water filters for Villa Angkasa condominium
2002 ABB Malaysia Overhaul ,site alignment and commission 5MW crusher motor and re-babitting of sleeve bearings using Hoyts 11RVirgin metal
2002 Matsushita Shah Alam Complete Overhaul of multistage chiller pumps, 30Kw
2002 TNB Connaught Bridge White-metal Bearing Inspection ,3.5MW Siemens AC motor
2002 ABB Malaysia Complete Overhaul Carlsberg brewery 450Kw motors
2002 ABB Malaysia Site overhaul KLCC GDC Turbine Generator 1MW